BUILDER
Granite & Grove
PROTOTYPESample builder record: names, projects and complaint counts are illustrative.
Delivered 7 projects since 2017: 5 on time, 2 late by 10 months on average. 19 RERA complaints, or 6.1 per 1,000 homes (average across builders: 3.2). 14 projects listed with us now.
Delivery record
| Project | RERA date | Delivered | Result |
|---|---|---|---|
| Sunrise Courtyard Greater Noida West, Delhi NCR | Dec 2024 | Dec 2024 | On time |
| Royal Enclave Greater Noida West, Delhi NCR | Dec 2022 | Sep 2023 | 9 mo late |
| Royal Enclave Yelahanka, Bengaluru | Dec 2021 | Nov 2022 | 11 mo late |
| Emerald Heights Yelahanka, Bengaluru | Dec 2020 | Dec 2020 | On time |
| Orchid Residences Kondapur, Hyderabad | Dec 2019 | Dec 2019 | On time |
| Harmony Gardens Panvel, Mumbai | Dec 2018 | Dec 2018 | On time |
| Royal Gardens Noida Sector 79, Delhi NCR | Dec 2017 | Dec 2017 | On time |
RERA complaints, in context
Complaints per 1,000 homes delivered. 19 complaints in total, 11 resolved. Most are about delays and refunds; read the orders on the portal.
Projects listed now
Delhi NCR
₹37 L+
₹68 L+
₹1.09 Cr+
₹1.1 Cr+
Bengaluru
₹73 L+
₹1.46 Cr+
₹1.21 Cr+
₹42 L+
Sample record for the prototype. Live version: built from RERA registrations, completion certificates and complaint orders, with dates. Last updated 3 Oct 2026. How we compute these →